Light-gray cottage with paired dormers, a covered entry and a deep green front lawn beside a burgundy Japanese maple.

In Junction City, New Homes Wait for the Sewer Plant

October 22, 2026

In most Lane County towns, buyer demand and builders' timelines decide how many new homes go up each year. Junction City works differently. Since December 2, 2024, every new home there has needed a sewer hookup, and hookups are capped under an agreement with Oregon's Department of Environmental Quality. The cap rises a little each time the city finishes a required task. In June 2026, Public Works Director Gary Kaping told the City Council that the city had 90 hookups available and that all of them were spoken for.

If you're comparing Junction City with Eugene, Springfield or Coburg, this matters more than any price chart. It decides what you can buy here over the next few years.

Ninety Hookups, and a Line for Them

The agreement is a Mutual Agreement and Order, or MAO. It covers the city's wastewater permit for discharging treated water into Flat Creek. According to the May 12, 2026 City Council packet, the MAO sets "stringent facility connection limitations," which stood at 91 equivalent dwelling units, or EDUs, at that point. Each completed milestone frees only "10 to 50 more connections," and the agreement's anticipated term is 10 years.

Six weeks later, the June 23 council minutes record Kaping's explanation of how the hookups are handed out. Requests are first come, first served. As new EDUs open up, he alternates among developers to let them know. Staff track every request and hookup in writing. DEQ doesn't count an EDU as connected until the home is occupied.

That last rule decides when a home counts. A finished house that nobody has moved into hasn't used up its hookup yet. So a hookup a builder has lined up isn't counted until a buyer moves in, and the 90 that are spoken for may not show up as completed homes for some time.

The city also has a land-use moratorium on development, adopted October 22, 2024, under ORS 197.505 to 197.540. It has been extended on May 13, 2025, on November 12, 2025, and a third time effective June 10, 2026. The current extension runs through December 10, 2026.

How the Cap Grows

The city's August 2026 wastewater strategic planning report lists the MAO's connection schedule. Each new allowance depends on a task being completed, not on a date:

Milestone the city must complete New connections allowed, up to
Before any compliance tasks 20 EDUs
Compliance task 5 20 EDUs
Compliance task 7 20 EDUs
Compliance task 8 30 EDUs
Compliance tasks 9 and 10, each 20 EDUs
Predesign reports for Subprojects 1 and 2, each 30 EDUs
Updated draft Facilities Plan 30 EDUs
Final design reports for Subprojects 1 and 2, each 30 EDUs
Construction and startup of Subproject 1 30 EDUs

The report says these are "cumulative connections that can be made once the City accomplishes the tasks." Several of the later steps are design and construction milestones for a treatment system. As the next sections show, that system's design is still undecided.

The Projects Already in Line

Several named projects are already moving through city review:

  • Rolling Meadows Phase 3. This 19-lot project on 3.32 acres was formerly called Phase 5, 1st Addition. The applicant is Pacific National Development, Inc. Most lots are planned for single-family homes, and two are planned for attached single-family homes. The application was deemed complete April 21, 2026, and Planning Commission review was scheduled for May 19, 2026.
  • The Reserve at Junction City Phase 3. West Linn Corporate Park, LLC submitted a final plat application in May 2025. Its narrative describes 80 single-family lots on 80.31 acres. An earlier summary in the same file says 85 lots.
  • Junction City Apartments. This is a 126-unit project, also by Pacific National Development. Because engineering wasn't finished, the city extended its development approval to March 24, 2027.

Together, those three projects add up to more than 220 planned homes and apartments, against a pool of 90 hookups that were already spoken for. City records don't say which project holds which hookups or how many EDUs an apartment unit counts as. Still, the numbers make the timing clear. When Lookout Eugene-Springfield reported on the wastewater question in July, City Administrator pro tem Spencer Nebel told the outlet that the city is letting permits go forward on a "rotating basis" for projects already on the books.

"Housing will be allowed on a very incremental basis until wastewater issues are addressed." Spencer Nebel, quoted by Lookout Eugene-Springfield

For a buyer, this means a new home in Junction City is usually one of a few dozen homes released per milestone, and the milestones arrive at the speed of compliance work. Existing homes already have their connections, so they aren't part of the queue.

What the Sales Numbers Show

The supply limit shows up in RMLS's Market Action report for Lane County. Here are the Junction City area figures for January through September of each year, with the countywide median for comparison:

January to September 2025 2026
Junction City new listings 204 155
Junction City pending sales 157 129
Junction City closed sales 142 131
Junction City median sale price $489,500 $411,200
Junction City average days on market 69 76
Lane County median sale price $444,700 $448,000

From January through September 2026, new listings in Junction City fell by about a quarter compared with the same months of 2025. Over the same period, the area's median sale price dropped below the Lane County median, after running well above it a year earlier. Measured over the 12 months ending in September 2026, Junction City's average sale price was down 15.1%, while Lane County's was down 0.4%.

RMLS doesn't break these figures out into new construction and resales. On their own, the numbers can't tell you why prices fell. With 131 closed sales, a handful of transactions can move the median a lot. What the table does show is a smaller market, with fewer listings, fewer pending sales and longer days on market, in a town where new construction is capped by sewer capacity. In September 2026 alone, the area had 48 active listings and 10 closed sales.

The Fix Has a Price Tag and a 2027 Answer Date

The connection cap stays until the city expands its wastewater capacity. The August report compares two main paths:

  • Build a new local plant. A moving bed bioreactor plant is estimated at $61.4 million, plus $1.18 million a year to operate.
  • Pipe wastewater to the regional plant. The second path would connect Junction City to the Metropolitan Wastewater Management Commission's facility in Eugene, piggybacking on a pipeline Lane County and Creswell are pursuing to serve Goshen. It's estimated at about $43.4 million, including buy-in and connection costs, plus $176,800 a year to operate.

The regional connection is the city's current preferred option. In the Lookout report, Nebel put the project at more than $50 million, which "would require bonding that ratepayers would support through increased rates." The city's report and that quote don't explain the gap between the two figures.

The dates that decide which path wins all fall in 2027 or later:

  1. December 9, 2025. The city reported winning a $3 million grant and a $3 million low-interest loan for wastewater work, and opened talks about connecting to the regional system.
  2. March 3, 2026. Lane County commissioners started the Metro Plan amendment that the connection requires. The goal is to finish it by fall 2027.
  3. September 8, 2026. The council approved agreements with Lane County and Creswell to fund a shared project manager. The county pays $100,000 a year, and Junction City and Creswell pay up to $50,000 a year each.
  4. October 13, 2026. A resolution to expand the urban growth boundary to take in city-owned land, under the "Junction City Future-Ready Utilities Project," was on the council agenda. That land would be needed for a local treatment plant if the regional connection falls through.
  5. November 2027. City staff expect to know by then whether the regional connection is feasible.

Utility bills are part of the cost of owning a home here. On July 20, 2026, water rates rose 8% and sewer rates rose 5%, which adds about $5.30 a month to the average residential bill. The July council packet notes that Junction City's rates were the lowest among comparable cities and stay toward the bottom even after the increase. That increase covers operating costs. Bonding for the larger project would come on top of it.

December 10 Is the Next Date to Watch

The third moratorium extension tells the council to decide, by December 10, 2026, whether to extend, revise or repeal the moratorium. The resolution itself anticipates that another extension or a replacement may be needed. The October 13 council agenda had no moratorium item.

Whatever the council decides in December, the DEQ connection cap stays in place until the required improvements are finished.

A Few Questions Buyers Ask

Does the cap apply to homes that are already built? The cap limits new connections to the sewer system. Existing homes are already connected.

Could connection fees change? Council minutes show water system development charges were last updated in 2005 and sewer charges in 2007, and the city has said it plans to review its fees and those charges. In April 2026, the council also approved a $13,600 consultant contract to calculate what regional sewer system development charges might cost.

Where can I follow the decisions? The city posts council and Planning Commission packets and minutes at junctioncityoregon.gov. The December moratorium review and the wastewater updates will show up there first.

This post is general information, not legal, tax or financial advice. If a moratorium, fee or utility rate affects your purchase, confirm the details with the city and the right professional.

At Parker Heights Realty, our office is right here in Junction City, and we follow the sewer queue as closely as the listings. If you're weighing a new build here against an existing home or against a home elsewhere in Lane County, schedule a free consultation and home valuation. We'll go through the hookup timeline and the September numbers with you, using your own price range.

Work With Us

We pride ourselves in providing personalized solutions that bring our clients closer to their dream properties and enhance their long-term wealth. Contact us today to find out how we can be of assistance to you!