October 8, 2026
Willamalane Park and Recreation District is working on playgrounds at four Springfield parks this fall. The district put out one announcement for all four, but the projects are on very different footing. Two have committed funding and posted closure windows. The other two parks had their climbing structures taken out over safety concerns, and the replacement date is "later this year."
The gap matters most at the parks that still look open. Closures at Meadow Park and Tyson Park both appear on the district's alerts page. Lively Park in Thurston and Willamalane Park on G Street aren't listed for any playground closure. Even so, the district says it removed the climbing structures at both parks.
| Park | Address | What's happening | Stated timing |
|---|---|---|---|
| Meadow Park | 851 Mill Street | Playground closed for new accessible surfacing | Closed Sept. 28 for about three to four weeks |
| Tyson Park | 3405 E Street | Whole park closed for redevelopment, new playground included | Wording varies: October, later this fall, or end of 2026 |
| Lively Park | 6100 Thurston Road | Climbing structure removed over safety concerns | Replacement "later this year" |
| Willamalane Park | 1276 G Street | Climbing structure removed over safety concerns | Replacement "later this year" |
Meadow and Tyson have their own line items, dollar figures and a project page. Lively and Willamalane Park get one sentence in the district's Sept. 23 release.
On Sept. 9, the Willamalane board approved a $162,836.64 contract to resurface the Meadow Park playground near downtown Springfield. The Willamalane Park Foundation is paying for it. The playground closed Sept. 28, and the district estimated three to four weeks of work. If that estimate holds, Meadow's playground should reopen in the second half of October. The district hadn't posted a reopening notice as of today.
Whitney Hoshaw, Willamalane's marketing and communications manager, told KEZI the new surfacing "has been needed for a while." She also said the district paired the Meadow job with Tyson so both could use the same contractor and equipment. The district says the surfacing at both parks also moves forward its long-term ADA Transition Plan, its roadmap for accessibility upgrades across parks and facilities.
Willamalane Executive Director Michael Wargo described the approach in the release:
"Thanks to generous support from Willamalane Park Foundation and by combining projects, we're able to make important improvements while making the most of available resources."
Tyson is a four-acre park in north-central Springfield. It runs along E Street on its north side, and 34th and 35th streets dead-end at its southern edge. When Lookout Eugene-Springfield photographed the old playground on Dec. 30, 2025, it was about 30 years old.
The rebuild follows a long timeline. Willamalane gathered public input in February and March 2024. Between April 2024 and September 2025, the City of Springfield required emergency access routes, which pushed the project back. Bidding opened in April 2026. The routes will be 10-foot-wide concrete paths connecting to 34th and 35th streets, with fold-down bollards to keep out everyday traffic. Willamalane landscape architect Simon Daws said the routes will look like "a 10-foot wide sidewalk" once the park is in use.
The new playground has two structures, one for kids ages 5 to 12 and a smaller one for younger children, plus spinners, rockers and swings. The redesigned park also includes:
Daws said the garden is a response to "quite high demand for community garden space within Springfield."
The playground has visibly progressed. The photo at the top of the district's Sept. 23 release shows colorful playground pieces stacked on the dirt where the new structures will go. The finish date is less clear. The project page gives June through October 2026 for construction, its timeline lists end of 2026 as the estimated completion, the alerts page says the park is closed through late fall, and the Sept. 23 release says work should wrap up "later this fall." The project page adds that the timeline "may shift as needed."
Tyson's funding comes from nearly $700,000 in grants, a $200,000 gift from the Willamalane Park Foundation and system development charges. Lookout reported the grants as $345,000 from the state's Local Government Grant Program and $350,000 from a federal Thriving Communities grant. Back then, the construction estimate was $1.05 million, set before the emergency routes were added. Daws said some parts of the site plan could move to a future phase if bids came in over budget. The public material doesn't name a contractor or a final award amount.
Add the $200,000 Tyson gift to the Foundation-funded Meadow contract and you get roughly the "nearly $400,000" the district credits to the Foundation. The district says that money made the Tyson and Meadow playground work possible "almost entirely through grants and donations." The Foundation is a separate, all-volunteer nonprofit, formed in 1983, that works alongside the district. Board President Ronelle Kuhnhenn said in the release that "this year, the foundation increased its support for important projects in Springfield."
The release doesn't say where the money for Lively and Willamalane Park comes from. The structures there came out because of safety concerns, and the only timing the district has given for replacements is "later this year."
Lively Park at 6100 Thurston Road is the main park on this list for families in Thurston. Its playground covers 8,000 square feet. The climbing structure is gone for now. Separately, Splash, the indoor water park at Lively Park, has been closed for annual fall maintenance since Sept. 28. In the meantime, Willamalane Park Swim Center has added hours and offerings. Willamalane Park, 1276 G Street, sits right beside that swim center, and its climbing structure has been removed too. That means the pool families are being sent to for now shares a park with a playground still waiting on its own replacement.
The district hasn't said whether the rest of either playground will close while the new structures go in. For now, the alerts page is the only place a closure would show up.
Willamalane's fall calendar keeps going while the playgrounds are torn up. Here are the dated events, in order:
Lively Park's new climbing structure could be in by Thanksgiving morning. Nothing the district has published so far says whether it will be.
When these playgrounds reopen and Tyson's garden plots start filling up, the parks become part of what nearby homes have going for them. If you're near Tyson, Meadow, Lively or Willamalane Park and wondering how the rebuild could affect your home's value, Parker Heights Realty can walk you through it. Schedule a free consultation and home valuation.